Complete a pre-startup safety review

Practice the sequence you already learned for “Complete a pre-startup safety review” until the order feels automatic. Drill OSHA 1910.119 PSSR from process-safety training. Hydrocarbons or hazardous chemicals are not introduced until punchlist safety items are closed.

  1. Confirm construction is in accordance with the design.
  2. Verify safety, operating, maintenance, and emergency procedures are in place.
  3. Confirm training is complete for the operating crew.
  4. Walk down punchlist items that affect safe operation and close them.
  5. Obtain the authorized PSSR signatures.
  6. Only then introduce hazardous chemicals or raise the unit to operating conditions.