Complete a group lockout with a lockbox
Practice the OSHA 1910.147(f)(3) group-lockout order from authorized-employee training. Personal locks do not come off the box until each worker is clear, and only the primary employee restores energy.
- Isolate all energy sources as the primary authorized employee.
- Verify zero energy as the primary authorized employee.
- Place the isolation-device keys in the group lockbox.
- Have each authorized employee verify isolation.
- Have each authorized employee apply a personal lock to the box.
- Each person removes only their own lock when their work is done.
- Confirm nonessential items are removed and equipment is intact.
- Confirm all employees are clear of the area.
- The primary employee restores energy only after the last personal lock is off.